Borden Elementary School

Project Summary

The Borden Elementary School project was part of a 5 campus project for West Clark Community Schools. Campus buildings were on 7 different land levels. Had to tie all that together. Halfway through the project, we discovered an old underground fuel tank leak and an old building foundation. Additionally, we had to design and build ramps to connect all the buildings. We developed a phasing plan to perform all work while school was fully occupied. This project was on time and under budget.

Project Stats

  • Part of Phase 1 for a $55 million dollar project that spanned five campuses in West Clark Community Schools
  • School remained open during renovation
  • On schedule
  • Within budget

“Shireman makes every effort possible to satisfy the customer. They take great pride in their work. They do it correctly, on time, and under budget.”